Finance & Investment Popular

EVM Calculator — Earned Value Management 2026

Calculate project EVM metrics: CV, SV, CPI, SPI, and Estimate at Completion (EAC).

EVM Calculator — Earned Value Management 2026

Instant real-time calculation

Budgeted cost of work scheduled by this date.

$

Budgeted value of work actually completed.

$

Actual total money spent to date.

$

Total approved total project budget.

$
Calculation Output
Result
CPI: 0.94 | SPI: 0.92Project Efficiency Indices
Minor Cost/Schedule Slip
47.0
Minor Cost/Schedule Slip
Detailed Breakdown
Cost Performance Index (CPI)0.94
Schedule Performance Index (SPI)0.92
Cost Variance (CV)$-6,000
Schedule Variance (SV)$-8,000
Estimate at Completion (EAC)$266,304
Variance at Completion (VAC)$-16,304
Warning: Cost Performance Index is 0.94 (every $1 spent yields only $0.94 of completed work). At this burn efficiency, projected project completion cost (EAC) will be $266,304, an overrun of $16,304 above original budget.

Comprehensive Guide to EVM Calculator — Earned Value Management 2026

Earned Value Management (EVM) Standards for 2026

Earned Value Management (EVM) is a project management methodology that integrates project scope, actual cost, and schedule timelines. Mandated on U.S. federal and major defense contracts (EIA-748), EVM answers: How much physical work has the team actually delivered compared to what was planned and what was spent?

A project that is under budget may not be doing well if it has only completed 30% of scheduled tasks. EVM reveals whether savings reflect genuine cost efficiency or missed project milestones.

EVM Performance Index Reference Table

CPI / SPI ValueStatus DefinitionMeaning for Project ExecutivesRecommended Action
> 1.0ExceptionalDelivering more value than planned/spentDocument best practices; release contingency budget
1.0Exact TargetProject executing precisely to baselineMaintain baseline tracking cadences
0.90 – 0.99Warning ZoneSlight cost overrun or schedule slipFast-track parallel tasks; control overtime
< 0.90Critical RiskSevere overrun; project failing baselineConduct formal re-baselining or scope reduction

The Core PMBOK EVM Equations

\text{Cost Variance (CV)} = EV - AC
\text{Schedule Variance (SV)} = EV - PV
\text{Cost Performance Index (CPI)} = \frac{EV}{AC}
\text{Schedule Performance Index (SPI)} = \frac{EV}{PV}
\text{Estimate at Completion (EAC)} = \frac{BAC}{CPI}

Frequently Asked Questions About EVM Calculator — Earned Value Management 2026

An SPI below 1.0 indicates that the project is progressing slower than scheduled. For example, an SPI of 0.80 means work is proceeding at only 80% of the planned schedule velocity.